March is here (Already) so we thought it would be a good idea to give you an overview of the current production line. So here it is…
Toulouse Production:
MSN002 (Private) – Currently in Refitting Hangar.
MSN042 (Emirates #13) – In Second Second Stage of Final Assembly and is Scheduled to Be Rolled Out in late March.
MSN047 (Qantas #7) – Engines Have Been Re Installed and Should Roll Out this week.
MSN048 (Lufthansa #4) – Completed and will be Rolled Out this week.
MSN050 (Qantas #8) – Being Stored in a Flightline Hangar until May.
MSN052 (Air France #5) – Completed and will be Rolled Out this week.
MSN055 (Qantas #9) – First Stage of Final Assembly. Parts of Final Assembly Will be done in a Flightline Hangar.
MSN056 (Emirates #14) – Second Stage of Final Assembly.
MSN057 (Emirates #15) – Waiting for slot in Second Stage of Final Assembly.
MSN058 (Singapore Airlines #12) – Waiting for Slot in First Stage of Final Assembly.
MSN061 (Lufthansa #5) – First Stage of Final Assembly.
MSN062 (Qantas #10) – First Stage of Final Assembly.
MSN065 (Singapore Airlines #13) – Body Join has Begun and is Scheduled to take 10 days.
Hamburg Production:
MSN009 (Emirates #9) – Delivery Scheduled for May.
MSN028 (Emirates #10) – Delivery Scheduled for June.
MSN030 (Emirates #11) – Delivery Scheduled for July.
MSN038 (Lufthansa #1) – Delivery Scheduled for 10th May.
MSN041 (Lufthansa #2) – Delivery Scheduled for June.
MSN043 (Air France #3) – Delivery Scheduled for April.
MSN044 (Lufthansa #3) – Delivery Scheduled for Q3 2010.
MSN046 (Emirates #12) – Delivery Scheduled for August.
MSN049 (AIr France #4) – Delivery Scheduled for Q3 2010,
MSN051 (Singapore Airlines #11) – Delivery Scheduled for Late March.
Convoy’s:
The next new frames to be Convoyed to Toulouse are scheduled to be.
MSN031 (China Southern #1)
MSN066 (Lufthansa #6)
MSN069 (Lufthansa #7)
MSN035 (Korean Air #1)
First Stage of Final Assembly = Installation of Electronic Components that Control the Aircraft and Installation of Fuel Tanks.
Second Stage of Final Assembly = Installation of Engines, Belly Fairing and all other Facilities in and outside the Aircraft.
Roll Out = Moved from the Final Assembly Line to the Flightline.
MSN051 will now have its interior installed. And delivery is scheduled for January 2010.